System Sign-Off
G2 Schedule of Test Results
G2 combines selected project circuits, available device data, measured results and test-instrument records.
Include Circuits (G2)
Only populated project circuits are offered. Expand a distro or circuit to review its assigned equipment or manual load and the available Engineering information before inclusion.
Selecting a circuit creates its G2 row and prepopulates the description and available device information. Automatic values remain overwritable.
Completing circuit rows
Record final-circuit status, fixed or adjustable RCD information, delay, residual rating, test method, polarity, phase sequence, earth fault loop impedance, prospective short-circuit current and comments.
Use Remove row directly on G2 when a selected or manually added circuit should no longer appear; there is no need to navigate back to Include Circuits.
Manual circuit rows
Select Add blank circuit row for tested circuits not represented in the planner model. Enter their circuit and device information directly in the table, then complete the same measured-result fields.
Test instruments
Record the manufacturer, model, serial number and calibration information for the instruments used. Complete the G2 form only after the circuit schedule and instrument details have been reviewed.
G2 is for inspection and measured test information. Engineering forecasts do not replace competent on-site testing.